SYSTEM SW / 2026-08-01 / Program kickoff

Kicking Off the Atlas Flagship Software Schedule

차기 플래그십 Atlas 소프트웨어 일정 킥오프

내년 3월 출시 예정인 차기 플래그십 Atlas의 시스템 소프트웨어 개발 킥오프 회의입니다. 프로그램 관리, 커널·BSP, 플랫폼 프레임워크, SQE 팀이 개발 시작일, 주요 마일스톤, 완료 기준과 위험 요소를 합의합니다.

가상의 비즈니스 회의 · 중급~고급 · 2,216단어 · 약 18분

Hyejin Park · Program ManagementDaniel Cho · Kernel & BSPSora Han · Kernel & BSPRachel Kim · Platform FrameworkEthan Yoon · SQE

01 / English script

Attendance and Introductions

01 · Hyejin ParkProgram Management

Good morning, everyone, and thanks for joining on short notice. I think we have everybody, but let me do a quick roll call so we know who owns what from day one. I'm Hyejin from Program Management, and I'll be the software program manager for Atlas. Daniel, Sora, could you introduce yourselves first?

02 · Daniel ChoKernel & BSP

Sure. I'm Daniel, technical lead for Kernel and BSP. My team will own bring-up on the new Arvenna chipset, the kernel branch, and all the low-level drivers, so anything that touches the bootloader, power management, or storage will probably land on my desk.

03 · Sora HanKernel & BSP

And I'm Sora, also from Kernel and BSP. I'll be handling the integration side, which means merging vendor drops, keeping our patches rebased, and making sure the daily build actually boots. Daniel is the architect; I'm more of the plumber.

04 · Rachel KimPlatform Framework

I'm Rachel from Platform Framework. We cover the Android framework layer, system services, and the vendor interface. On Atlas, my biggest interest is how early we get a stable BSP, because every framework feature we plan is blocked until the hardware abstraction layers are in place.

05 · Ethan YoonSQE

Hi, I'm Ethan from SQE, software quality engineering. My team designs the test plans, runs the stability and regression campaigns, and ultimately signs off on each milestone. I'll be honest, I'm here today mostly to make sure the quality gates are written into the schedule rather than added at the end.

Agenda and Program Background

06 · Hyejin ParkProgram Management

Perfect, that's exactly the mindset I want. Here's the agenda. First, I'll give some background on Atlas and the commercial target. Second, we'll walk through a draft milestone plan and challenge it. Third, we'll talk about risks and dependencies. And finally, we'll confirm owners and the next checkpoint. We have an hour, so let's try to keep each part tight.

07 · Hyejin ParkProgram Management

So, background. Atlas is next year's flagship, and the business has committed to a market launch on March 12th, 2027. That date is announced internally and the marketing plan is built around it, so please treat it as fixed. What we control is everything between today and that date. The headline change from Orion is the new Arvenna chipset, plus a move to a newer kernel branch.

08 · Daniel ChoKernel & BSP

Can I add some context there? The new chipset is not just a speed bump. Arvenna redesigned the power management controller, and the memory controller is new as well. In my experience, those two areas account for most of the early instability. So when we look at the schedule, I'd like us to be realistic about how long bring-up will take.

09 · Hyejin ParkProgram Management

Noted, and that's a good segue. Let me share the draft. The first Arvenna BSP drop is promised for August 14th. Development officially starts on Monday, August 17th. We target first boot on proto hardware by September 7th, EVT software by October 19th, feature complete on December 4th, code freeze on January 22nd, and the final release candidate on February 5th.

Challenging the Milestone Plan

10 · Sora HanKernel & BSP

Just to clarify, when you say first boot on September 7th, do you mean booting to the Android home screen, or just getting a kernel console? Those are very different milestones, and I've seen people celebrate a console prompt while the display, storage, and USB were all still broken.

11 · Hyejin ParkProgram Management

Fair question. My draft says boot to home screen with display and touch working. Is that too aggressive?

12 · Daniel ChoKernel & BSP

Honestly, yes, if the BSP lands on the 14th. That gives us roughly three weeks, and the proto boards don't arrive in Korea until August 24th according to the hardware team. So realistically we'd have two weeks on real hardware. I'd push back on that. My proposal is to split it into two checkpoints: kernel console by September 7th and home screen by September 21st.

13 · Rachel KimPlatform Framework

I understand the hardware constraint, but from the framework side, two extra weeks without a booting system really hurts. My team is planning to start integrating the new camera and display features in September. If we can't boot to home until the 21st, we lose about a third of our integration window before EVT.

14 · Daniel ChoKernel & BSP

I hear you, Rachel, but committing to a date we're likely to miss doesn't help you either. What if we give your team early access to the reference board? Arvenna ships an evaluation board that already runs their BSP. It's not our hardware, but it's close enough for framework development in the meantime.

15 · Rachel KimPlatform Framework

That could work, as long as we get enough units. How many evaluation boards do we have?

16 · Sora HanKernel & BSP

We have six today, and four of them are reserved for kernel bring-up. I could free up two for your team immediately, and I'll ask Arvenna for another batch of ten. Their lead time is usually about two weeks, so we'd have them before the end of August.

17 · Ethan YoonSQE

Can I jump in on the later milestones? I'm less worried about September and more worried about the gap between feature complete and code freeze. December 4th to January 22nd looks like seven weeks, but it includes the year-end holidays. In practice, we lose at least a week and a half, and that's exactly when SQE needs to run the full stability campaign.

18 · Hyejin ParkProgram Management

How long does the full stability campaign need, end to end?

19 · Ethan YoonSQE

For a new chipset, I'd want four full cycles. Each cycle is about a week: a 72-hour stress run on two hundred devices, then triage and a fix build. If the defect count is still trending down after cycle three, we can be flexible. But I'm not comfortable signing off on a new platform with fewer than three cycles.

20 · Rachel KimPlatform Framework

Then the obvious question is whether feature complete can move earlier. My team could commit to November 27th instead of December 4th, but only if we really do get a booting device in mid-September. Those two things are tied together.

21 · Hyejin ParkProgram Management

I like where this is going. Let me try to summarize the trade-off. If we split first boot into console on September 7th and home screen on September 21st, and Rachel's team gets evaluation boards in the meantime, framework can pull feature complete in to November 27th. That gives SQE one extra week before the holidays. Does that hold together for everyone?

22 · Daniel ChoKernel & BSP

It does for kernel, with one caveat. Everything we just said assumes Arvenna delivers on August 14th. If their drop slips, the whole chain moves. I'd like a contingency trigger in the plan, something like: if the BSP is more than five working days late, we escalate to their account management and replan.

Risks and Dependencies

23 · Hyejin ParkProgram Management

That's a very reasonable trigger, and I'll put it in the risk register. Let's stay on risks for a moment. Apart from the BSP date, what keeps you up at night?

24 · Sora HanKernel & BSP

For me, it's the kernel branch move. We're carrying around three hundred out-of-tree patches from Orion. Some of them will apply cleanly, but a lot of them touch scheduler and memory code that changed upstream. I estimate four to six weeks of rebasing and retesting, running in parallel with bring-up. If I'm the only person on it, that's a single point of failure.

25 · Daniel ChoKernel & BSP

Agreed. I can move one more engineer onto the rebase from the Orion Fold team once their launch wraps up in mid-September. Until then, Sora, let's prioritize ruthlessly. Anything that's not needed for boot, display, or storage can wait.

26 · Rachel KimPlatform Framework

On my side, the dependency is Google. The Atlas schedule assumes we ship on the next Android release, and Google's public timeline for the final platform build is still a little vague. If their release slips by a month, our feature complete date doesn't mean much, because we'd be building on a moving base.

27 · Hyejin ParkProgram Management

Good point. I'll set up a separate session with our Google partner engineering contact to get their milestone dates in writing. Ethan, anything from the quality side beyond the holiday gap?

28 · Ethan YoonSQE

Two things. First, test device allocation. Two hundred devices for the stability campaign means we need DVT hardware by mid-December at the latest. Second, I want a written definition of done for each milestone. Last year we had a lot of debate about whether EVT was really complete, and it cost us time. If we agree on the exit criteria now, nobody has to argue later.

29 · Hyejin ParkProgram Management

Couldn't agree more. Can you draft exit criteria for EVT and feature complete, and circulate them by next Friday? Keep it measurable: open blocker count, crash rate per thousand hours, that kind of thing.

30 · Ethan YoonSQE

Will do. I'll base it on the Orion criteria and adjust the thresholds for a new chipset.

31 · Daniel ChoKernel & BSP

There's one more risk I want on the record, even if we can't do much about it today. Arvenna's thermal characterization for the new chipset won't be final until October. Until then, our thermal and power management tuning is based on preliminary data. If the final numbers come in worse, we could see throttling problems late in the program, which is the worst possible time.

32 · Hyejin ParkProgram Management

Understood. Let's log it as a known risk with an October review date, and ask Arvenna whether they can share interim measurements earlier. Even partial data would help us avoid surprises.

33 · Sora HanKernel & BSP

I can raise that in the first vendor sync. They usually have bench data long before the official report is signed off.

Working Agreements and Communication

34 · Hyejin ParkProgram Management

Before we lock the decisions, I want to spend ten minutes on how we work together, because in my experience, schedules rarely fail on technology alone. They fail when issues sit in somebody's queue for a week and nobody notices. So, how do we want to triage bugs during bring-up?

35 · Daniel ChoKernel & BSP

During bring-up, I'd suggest a short daily triage, fifteen minutes, kernel and BSP plus whoever is blocked. Not a status meeting, just a quick pass over new issues to assign an owner and a priority. The rule should be that no new blocker goes more than one working day without an owner.

36 · Ethan YoonSQE

I'd add one thing to that. Every issue SQE files will include the build number, the reproduction rate, and logs attached at the time of filing. In return, I'd ask developers not to close issues as 'cannot reproduce' without talking to us first. Half the time, the difference is a test condition that wasn't obvious from the ticket.

37 · Sora HanKernel & BSP

That's fair, and honestly it goes both ways. If you can give us the exact test script, we can often reproduce it on our own bench instead of borrowing your devices. That would take a lot of pressure off the device pool, which is going to be tight until DVT.

38 · Rachel KimPlatform Framework

From the framework side, my concern is visibility into vendor issues. When something is stuck with Arvenna, we usually find out late, because the ticket lives in their portal and not in our tracker. Could we mirror vendor tickets into our system so everyone can see the status in one place?

39 · Daniel ChoKernel & BSP

We tried a full mirror on Orion and it was more noise than signal. What worked better was a weekly vendor sync where we only review tickets that block one of our milestones. I'd propose we do that again and publish a short list of top vendor blockers after each sync.

40 · Rachel KimPlatform Framework

That works for me, as long as the list is actually published. I don't need every detail; I just need to know when to stop waiting and start working around a problem.

41 · Hyejin ParkProgram Management

Good, so we have three working agreements: a fifteen-minute daily triage during bring-up, no 'cannot reproduce' closures without talking to SQE, and a weekly vendor sync with a published blocker list. I'll capture those in the program charter so new team members can find them later.

Decisions and Action Items

42 · Hyejin ParkProgram Management

Great. Let me read back the decisions so we're all on the same page. One: development starts on August 17th. Two: first boot is split into kernel console by September 7th and home screen with display and touch by September 21st. Three: framework feature complete moves to November 27th. Four: code freeze stays on January 22nd and the final release candidate on February 5th. Any objections?

43 · Rachel KimPlatform Framework

No objection, as long as the evaluation boards show up on time.

44 · Hyejin ParkProgram Management

Understood, and that's an action item. Here are the owners. Sora: hand two evaluation boards to Rachel's team by Tuesday and request ten more from Arvenna this week. Daniel: confirm the August 14th BSP date with Arvenna in writing by Wednesday. Ethan: circulate draft exit criteria by Friday, August 7th. Rachel: share the framework integration plan against the new dates by the same Friday. And I'll set up the Google timeline call and update the risk register with the BSP escalation trigger.

45 · Sora HanKernel & BSP

One small request. Can we also agree on a weekly build health report? Just a one-page summary of whether the daily build boots, which tests pass, and what's blocking. It saves a lot of hallway questions.

46 · Hyejin ParkProgram Management

Great idea. Sora, would you own that, starting from the first week of development? Every Friday afternoon.

47 · Sora HanKernel & BSP

Happy to.

Closing and Next Meeting

48 · Hyejin ParkProgram Management

Then let's wrap up. Thank you all for pushing back where it mattered. I'd much rather adjust the plan today than discover in November that it was never realistic. Our next checkpoint is Saturday, August 8th, at 10 a.m. Korea time, same meeting room and the same video link. By then, I expect the BSP date confirmed and the exit criteria drafted.

49 · Daniel ChoKernel & BSP

Sounds good. I'll ping Arvenna right after this call.

50 · Ethan YoonSQE

Thanks, Hyejin. This was a productive kickoff. See you all next week.

02 / 한국어 번역

참석자 확인 및 소개

01 · Hyejin ParkProgram Management

여러분, 좋은 아침입니다. 급하게 잡은 회의인데 참석해 주셔서 감사합니다. 다 오신 것 같지만, 첫날부터 누가 무엇을 맡는지 분명히 하기 위해 간단히 출석을 확인하겠습니다. 저는 프로그램 관리팀의 혜진이고, Atlas의 소프트웨어 프로그램 매니저를 맡게 됩니다. Daniel, Sora, 먼저 소개 부탁드려요.

02 · Daniel ChoKernel & BSP

네. 저는 커널·BSP 기술 리드 Daniel입니다. 저희 팀은 새 Arvenna 칩셋의 브링업, 커널 브랜치, 그리고 모든 저수준 드라이버를 맡습니다. 그래서 부트로더, 전원 관리, 스토리지에 관련된 일은 대부분 제 쪽으로 올 겁니다.

03 · Sora HanKernel & BSP

저는 같은 커널·BSP 팀의 Sora입니다. 저는 통합 쪽을 맡는데, 벤더 드롭을 머지하고, 우리 패치를 계속 리베이스하고, 데일리 빌드가 실제로 부팅되는지 확인하는 일입니다. Daniel이 설계자라면 저는 배관공에 가깝죠.

04 · Rachel KimPlatform Framework

저는 플랫폼 프레임워크팀의 Rachel입니다. 저희는 안드로이드 프레임워크 계층, 시스템 서비스, 벤더 인터페이스를 담당합니다. Atlas에서 제가 가장 신경 쓰는 건 안정적인 BSP를 얼마나 빨리 받느냐입니다. HAL이 갖춰지기 전까지는 저희가 계획한 프레임워크 기능이 전부 막혀 있거든요.

05 · Ethan YoonSQE

안녕하세요, SQE, 즉 소프트웨어 품질 엔지니어링팀의 Ethan입니다. 저희 팀은 테스트 계획을 설계하고, 안정성과 회귀 테스트를 수행하고, 최종적으로 각 마일스톤을 승인합니다. 솔직히 오늘은 품질 게이트가 마지막에 덧붙여지는 게 아니라 일정에 처음부터 들어가도록 확인하려고 왔습니다.

안건 및 프로그램 배경

06 · Hyejin ParkProgram Management

좋아요, 제가 원하는 게 바로 그런 자세입니다. 안건을 말씀드리겠습니다. 첫째, Atlas와 사업 목표에 대한 배경을 설명하겠습니다. 둘째, 마일스톤 계획 초안을 함께 보면서 검증하겠습니다. 셋째, 위험 요소와 의존 관계를 이야기하겠습니다. 마지막으로 담당자와 다음 점검 일정을 확정하겠습니다. 한 시간밖에 없으니 각 파트를 짧게 진행해 봅시다.

07 · Hyejin ParkProgram Management

그럼 배경부터 보죠. Atlas는 내년 플래그십이고, 사업부는 2027년 3월 12일 시장 출시를 확정했습니다. 이 날짜는 내부에 공지됐고 마케팅 계획도 여기에 맞춰져 있으니 고정된 날짜로 생각해 주세요. 우리가 조정할 수 있는 건 오늘부터 그날까지의 모든 것입니다. Orion 대비 가장 큰 변화는 새 Arvenna 칩셋이고, 더 최신 커널 브랜치로의 전환도 있습니다.

08 · Daniel ChoKernel & BSP

거기에 맥락을 좀 더해도 될까요? 새 칩셋은 단순히 성능만 올라간 게 아닙니다. Arvenna가 전원 관리 컨트롤러를 재설계했고, 메모리 컨트롤러도 새로 바뀌었습니다. 제 경험상 초기 불안정성의 대부분이 이 두 영역에서 나옵니다. 그래서 일정을 볼 때 브링업 기간을 현실적으로 잡았으면 합니다.

09 · Hyejin ParkProgram Management

알겠습니다. 마침 다음 이야기로 넘어가기 좋네요. 초안을 공유하겠습니다. Arvenna의 첫 BSP 드롭은 8월 14일로 약속되어 있습니다. 개발은 8월 17일 월요일에 공식적으로 시작합니다. 9월 7일까지 프로토 하드웨어 첫 부팅, 10월 19일까지 EVT 소프트웨어, 12월 4일 기능 완료, 1월 22일 코드 프리즈, 2월 5일 최종 릴리스 후보를 목표로 합니다.

마일스톤 계획 검토와 이견 조율

10 · Sora HanKernel & BSP

확인차 여쭤볼게요. 9월 7일 첫 부팅이라는 게 안드로이드 홈 화면까지 부팅하는 건가요, 아니면 커널 콘솔만 뜨는 건가요? 둘은 완전히 다른 마일스톤이고, 디스플레이, 스토리지, USB가 다 안 되는 상태에서 콘솔 프롬프트만 보고 축하하는 경우를 본 적이 있거든요.

11 · Hyejin ParkProgram Management

좋은 질문입니다. 제 초안은 디스플레이와 터치가 동작하는 상태로 홈 화면까지 부팅하는 겁니다. 너무 공격적인가요?

12 · Daniel ChoKernel & BSP

솔직히 BSP가 14일에 들어온다면 그렇습니다. 그러면 약 3주인데, 하드웨어팀 말로는 프로토 보드가 8월 24일에야 한국에 도착합니다. 실제 하드웨어로 작업할 수 있는 건 현실적으로 2주 정도죠. 그 부분은 반대 의견을 내고 싶습니다. 두 개의 체크포인트로 나누자는 게 제 제안입니다. 9월 7일까지 커널 콘솔, 9월 21일까지 홈 화면이요.

13 · Rachel KimPlatform Framework

하드웨어 제약은 이해하지만, 프레임워크 입장에서는 부팅되는 시스템 없이 2주가 더 늘어나는 게 정말 타격이 큽니다. 저희 팀은 9월에 새 카메라와 디스플레이 기능 통합을 시작할 계획입니다. 21일까지 홈 화면 부팅이 안 되면 EVT 전 통합 기간의 약 3분의 1을 잃게 됩니다.

14 · Daniel ChoKernel & BSP

Rachel, 무슨 말인지 알겠어요. 하지만 놓칠 가능성이 큰 날짜를 약속하는 것도 도움이 안 됩니다. 대신 Rachel 팀에 레퍼런스 보드를 먼저 제공하면 어떨까요? Arvenna가 자기네 BSP가 이미 돌아가는 평가 보드를 제공하거든요. 우리 하드웨어는 아니지만, 그동안 프레임워크 개발을 하기에는 충분히 비슷합니다.

15 · Rachel KimPlatform Framework

보드를 충분히 받을 수 있다면 괜찮을 것 같아요. 평가 보드는 몇 대나 있나요?

16 · Sora HanKernel & BSP

현재 6대가 있고, 그중 4대는 커널 브링업용으로 예약돼 있습니다. Rachel 팀에 2대는 바로 내드릴 수 있고, Arvenna에 10대를 추가로 요청하겠습니다. 보통 리드 타임이 2주 정도니까 8월 말 전에는 받을 수 있을 겁니다.

17 · Ethan YoonSQE

뒤쪽 마일스톤에 대해 말씀드려도 될까요? 저는 9월보다 기능 완료와 코드 프리즈 사이의 간격이 더 걱정됩니다. 12월 4일부터 1월 22일까지가 7주처럼 보이지만, 연말 휴가가 끼어 있습니다. 실제로는 최소 1주 반은 날아가는데, 그때가 바로 SQE가 전체 안정성 테스트를 돌려야 하는 시기입니다.

18 · Hyejin ParkProgram Management

전체 안정성 테스트는 처음부터 끝까지 얼마나 걸리나요?

19 · Ethan YoonSQE

새 칩셋이라면 네 번의 전체 사이클을 원합니다. 한 사이클은 약 일주일입니다. 200대 단말로 72시간 스트레스 테스트를 돌리고, 분석한 다음 수정 빌드를 만드는 겁니다. 세 번째 사이클 이후에도 결함 수가 계속 줄어드는 추세라면 유연하게 갈 수 있습니다. 하지만 새 플랫폼을 세 사이클 미만으로 승인하는 건 마음이 편치 않습니다.

20 · Rachel KimPlatform Framework

그렇다면 당연히 기능 완료를 앞당길 수 있느냐는 질문이 나오겠죠. 저희 팀은 12월 4일 대신 11월 27일로 약속할 수 있지만, 9월 중순에 정말로 부팅되는 단말을 받는다는 전제에서만 가능합니다. 그 두 가지는 맞물려 있어요.

21 · Hyejin ParkProgram Management

이야기가 좋은 방향으로 가네요. 트레이드오프를 정리해 보겠습니다. 첫 부팅을 9월 7일 콘솔, 9월 21일 홈 화면으로 나누고, 그동안 Rachel 팀이 평가 보드를 쓰면, 프레임워크는 기능 완료를 11월 27일로 당길 수 있습니다. 그러면 SQE는 휴가 전에 일주일을 더 확보합니다. 모두에게 앞뒤가 맞나요?

22 · Daniel ChoKernel & BSP

커널 쪽은 괜찮습니다. 단, 조건이 하나 있어요. 방금 말한 모든 게 Arvenna가 8월 14일에 납품한다는 전제입니다. 드롭이 밀리면 전체가 다 밀립니다. 계획에 비상 트리거를 넣었으면 해요. 예를 들어 BSP가 영업일 기준 5일 이상 늦으면 그쪽 어카운트 매니지먼트에 에스컬레이션하고 일정을 다시 짜는 식으로요.

위험 요소와 의존 관계

23 · Hyejin ParkProgram Management

아주 합리적인 트리거네요. 리스크 레지스터에 넣겠습니다. 잠깐 위험 요소에 대해 더 이야기해 봅시다. BSP 날짜 말고 밤잠을 설치게 하는 게 뭐가 있나요?

24 · Sora HanKernel & BSP

저는 커널 브랜치 전환입니다. Orion에서 가져온 아웃오브트리 패치가 약 300개입니다. 일부는 깔끔하게 적용되겠지만, 상당수가 업스트림에서 바뀐 스케줄러와 메모리 코드를 건드립니다. 브링업과 병행해서 리베이스와 재테스트에 4~6주가 걸릴 것으로 봅니다. 저 혼자 맡으면 단일 장애점이 되는 거죠.

25 · Daniel ChoKernel & BSP

동의합니다. 9월 중순 Orion Fold 출시가 마무리되면 그 팀에서 엔지니어 한 명을 리베이스에 더 붙일 수 있어요. 그때까지는 Sora, 철저하게 우선순위를 정합시다. 부팅, 디스플레이, 스토리지에 필요하지 않은 건 모두 뒤로 미뤄도 됩니다.

26 · Rachel KimPlatform Framework

제 쪽은 Google 의존성이 있습니다. Atlas 일정은 다음 안드로이드 릴리스로 출시한다는 전제인데, 최종 플랫폼 빌드에 대한 Google의 공개 일정이 아직 좀 모호합니다. 그쪽 릴리스가 한 달 밀리면, 계속 바뀌는 기반 위에서 개발하는 셈이라 우리 기능 완료 날짜가 큰 의미가 없어집니다.

27 · Hyejin ParkProgram Management

좋은 지적이에요. Google 파트너 엔지니어링 담당자와 별도 세션을 잡아서 마일스톤 날짜를 서면으로 받아 두겠습니다. Ethan, 휴가 기간 문제 말고 품질 쪽에서 다른 건요?

28 · Ethan YoonSQE

두 가지입니다. 첫째는 테스트 단말 배정입니다. 안정성 테스트에 200대가 필요하다는 건 늦어도 12월 중순까지 DVT 하드웨어가 있어야 한다는 뜻입니다. 둘째, 각 마일스톤에 대한 완료 기준을 문서로 정했으면 합니다. 작년에 EVT가 정말 완료된 건지를 두고 논쟁이 많았고, 그 때문에 시간을 잃었거든요. 지금 종료 기준을 합의해 두면 나중에 아무도 싸울 필요가 없습니다.

29 · Hyejin ParkProgram Management

전적으로 동의합니다. EVT와 기능 완료에 대한 종료 기준 초안을 작성해서 다음 주 금요일까지 공유해 줄 수 있나요? 측정 가능하게 해 주세요. 미해결 블로커 수, 천 시간당 크래시율 같은 것들이요.

30 · Ethan YoonSQE

그렇게 하겠습니다. Orion 기준을 바탕으로 하고 새 칩셋에 맞게 기준치를 조정하겠습니다.

31 · Daniel ChoKernel & BSP

오늘 당장 할 수 있는 건 많지 않더라도 기록해 두고 싶은 위험이 하나 더 있습니다. 새 칩셋에 대한 Arvenna의 발열 특성 데이터가 10월이 되어야 확정됩니다. 그때까지 저희 발열·전원 관리 튜닝은 예비 데이터를 기반으로 합니다. 최종 수치가 더 나쁘게 나오면 프로그램 후반에 스로틀링 문제가 생길 수 있는데, 그게 최악의 타이밍이죠.

32 · Hyejin ParkProgram Management

알겠습니다. 10월 검토 날짜를 붙여 알려진 위험으로 기록하고, Arvenna에 중간 측정값을 더 일찍 공유해 줄 수 있는지 물어봅시다. 일부 데이터라도 예상치 못한 상황을 피하는 데 도움이 될 겁니다.

33 · Sora HanKernel & BSP

첫 번째 벤더 회의에서 그 얘기를 꺼내겠습니다. 보통 공식 보고서가 승인되기 훨씬 전에 벤치 데이터는 갖고 있거든요.

업무 방식과 소통 규칙

34 · Hyejin ParkProgram Management

결정 사항을 확정하기 전에, 함께 일하는 방식에 10분 정도 쓰고 싶어요. 제 경험상 일정은 기술 문제만으로 실패하는 경우가 드뭅니다. 이슈가 누군가의 큐에 일주일씩 묵혀 있는데 아무도 모를 때 실패하죠. 브링업 기간에 버그 분류는 어떻게 할까요?

35 · Daniel ChoKernel & BSP

브링업 기간에는 짧은 데일리 트리아지를 제안합니다. 15분 정도, 커널·BSP 팀과 막혀 있는 사람이 참석하는 거죠. 현황 회의가 아니라 새 이슈를 훑어보면서 담당자와 우선순위를 정하는 자리입니다. 원칙은 새로운 블로커가 담당자 없이 영업일 하루를 넘기지 않는 것이어야 합니다.

36 · Ethan YoonSQE

거기에 하나 덧붙이고 싶어요. SQE가 등록하는 모든 이슈에는 빌드 번호, 재현율, 그리고 등록 시점의 로그를 첨부하겠습니다. 대신 개발자분들은 저희와 먼저 이야기하지 않고 '재현 불가'로 이슈를 닫지 말아 주셨으면 합니다. 절반 정도는 티켓만 봐서는 알기 어려운 테스트 조건 차이 때문이거든요.

37 · Sora HanKernel & BSP

공정한 요청이고, 사실 그건 양방향이에요. 정확한 테스트 스크립트를 주시면 SQE 단말을 빌리지 않고 저희 벤치에서 재현할 수 있는 경우가 많습니다. DVT 전까지는 단말 수가 빠듯할 테니 그러면 단말 풀 부담이 많이 줄어들 겁니다.

38 · Rachel KimPlatform Framework

프레임워크 입장에서는 벤더 이슈의 가시성이 걱정입니다. 뭔가 Arvenna 쪽에서 막혀 있으면, 티켓이 우리 트래커가 아니라 그쪽 포털에 있어서 보통 늦게 알게 되거든요. 벤더 티켓을 우리 시스템에 미러링해서 모두가 한곳에서 상태를 볼 수 있게 할 수 있을까요?

39 · Daniel ChoKernel & BSP

Orion 때 전체 미러링을 해 봤는데 유용한 정보보다 잡음이 더 많았어요. 더 효과가 있었던 건 우리 마일스톤을 막는 티켓만 검토하는 주간 벤더 회의였습니다. 그 방식을 다시 하고, 매 회의 후에 주요 벤더 블로커 목록을 짧게 공유하자고 제안합니다.

40 · Rachel KimPlatform Framework

목록이 실제로 공유된다면 저는 괜찮습니다. 세부 내용까지는 필요 없고, 언제 기다리기를 멈추고 문제를 우회하기 시작해야 할지만 알면 돼요.

41 · Hyejin ParkProgram Management

좋습니다. 그럼 세 가지 업무 규칙이 생겼네요. 브링업 기간 15분 데일리 트리아지, SQE와 이야기하지 않고 '재현 불가'로 닫지 않기, 그리고 블로커 목록을 공유하는 주간 벤더 회의입니다. 나중에 새로 합류하는 팀원도 찾아볼 수 있게 프로그램 헌장에 정리해 두겠습니다.

결정 사항 및 실행 항목

42 · Hyejin ParkProgram Management

좋습니다. 모두 같은 이해를 갖도록 결정 사항을 다시 읽겠습니다. 첫째, 개발은 8월 17일에 시작합니다. 둘째, 첫 부팅은 9월 7일 커널 콘솔, 9월 21일 디스플레이와 터치가 되는 홈 화면으로 나눕니다. 셋째, 프레임워크 기능 완료는 11월 27일로 옮깁니다. 넷째, 코드 프리즈는 1월 22일, 최종 릴리스 후보는 2월 5일로 유지합니다. 이견 있나요?

43 · Rachel KimPlatform Framework

평가 보드가 제때 온다면 이견 없습니다.

44 · Hyejin ParkProgram Management

알겠습니다. 그게 하나의 실행 항목이에요. 담당자를 정리하겠습니다. Sora는 화요일까지 Rachel 팀에 평가 보드 2대를 전달하고, 이번 주에 Arvenna에 10대를 추가 요청해 주세요. Daniel은 수요일까지 Arvenna로부터 8월 14일 BSP 날짜를 서면으로 확인해 주세요. Ethan은 8월 7일 금요일까지 종료 기준 초안을 공유해 주세요. Rachel은 같은 금요일까지 새 일정에 맞춘 프레임워크 통합 계획을 공유해 주세요. 저는 Google 일정 회의를 잡고, BSP 에스컬레이션 트리거를 리스크 레지스터에 반영하겠습니다.

45 · Sora HanKernel & BSP

작은 요청이 하나 있어요. 주간 빌드 상태 보고서도 합의할 수 있을까요? 데일리 빌드가 부팅되는지, 어떤 테스트가 통과하는지, 무엇이 막고 있는지를 한 페이지로 요약하는 겁니다. 복도에서 받는 질문을 많이 줄여 줍니다.

46 · Hyejin ParkProgram Management

좋은 생각이에요. Sora가 개발 첫 주부터 맡아 줄 수 있나요? 매주 금요일 오후로요.

47 · Sora HanKernel & BSP

기꺼이요.

마무리 및 다음 회의

48 · Hyejin ParkProgram Management

그럼 마무리하겠습니다. 중요한 지점에서 반대 의견을 내 주셔서 모두 감사합니다. 11월에 가서야 계획이 처음부터 비현실적이었다는 걸 발견하는 것보다 오늘 계획을 조정하는 게 훨씬 낫습니다. 다음 점검 회의는 8월 8일 토요일 한국 시간 오전 10시, 같은 회의실과 같은 화상 링크입니다. 그때까지 BSP 날짜가 확정되고 종료 기준 초안이 나와 있기를 기대합니다.

49 · Daniel ChoKernel & BSP

좋습니다. 이 회의 끝나자마자 Arvenna에 연락하겠습니다.

50 · Ethan YoonSQE

감사합니다, 혜진 님. 생산적인 킥오프였어요. 다음 주에 뵙겠습니다.

03 / Business expressions

on short notice

급하게, 촉박한 통보로 · 갑자기 잡힌 회의나 요청에 응해 준 상대에게 감사할 때

Good morning, everyone, and thanks for joining on short notice.

응용 연습
Thanks for reviewing my patch on such short notice.

land on my desk

내 업무로 넘어오다 · 어떤 종류의 일이 결국 자신이 담당하게 된다고 말할 때

My team will own bring-up on the new Arvenna chipset, the kernel branch, and all the low-level drivers, so anything that touches the bootloader, power management, or storage will probably land on my desk.

응용 연습
Any crash in the display driver will land on my desk first.

treat it as fixed

확정된 것으로 간주하다 · 바꿀 수 없는 조건(출시일 등)을 전제로 계획하자고 할 때

That date is announced internally and the marketing plan is built around it, so please treat it as fixed.

응용 연습
The carrier certification date is contractual, so treat it as fixed.

a good segue

다음 주제로 넘어가기 좋은 연결 · 상대의 발언이 다음 안건과 자연스럽게 이어질 때

Noted, and that's a good segue.

응용 연습
That's a good segue into our next topic, the crash dashboard.

Just to clarify

확인차 여쭙자면 · 모호한 표현의 정확한 의미를 확인할 때

Just to clarify, when you say first boot on September 7th, do you mean booting to the Android home screen, or just getting a kernel console?

응용 연습
Just to clarify, does the fix apply to both the A and B partitions?

I'd push back on that

그 부분은 반대 의견을 내겠다 · 상대 제안이나 일정에 정중하지만 분명하게 이의를 제기할 때

I'd push back on that.

응용 연습
If the plan is to skip the regression run, I'd push back on that.

in the meantime

그동안, 그 사이에 · 본래 해결책이 나오기 전의 임시 방안을 말할 때

It's not our hardware, but it's close enough for framework development in the meantime.

응용 연습
In the meantime, let's disable the feature flag on beta builds.

Can I jump in

끼어들어도 될까요 · 회의 중 다른 사람의 이야기에 의견을 보태고 싶을 때

Can I jump in on the later milestones?

응용 연습
Can I jump in with a quick data point from last night's run?

end to end

처음부터 끝까지 전 과정 · 전체 과정의 소요 시간이나 범위를 물을 때

How long does the full stability campaign need, end to end?

응용 연습
How long does an OTA update take, end to end, on a full device?

tied together

서로 맞물려 있는 · 두 조건이나 일정이 서로 의존한다고 강조할 때

Those two things are tied together.

응용 연습
The kernel uplift and the vendor drop are tied together.

single point of failure

단일 장애점 · 한 사람이나 한 요소에 모든 것이 의존하는 위험을 지적할 때

If I'm the only person on it, that's a single point of failure.

응용 연습
Having one build server for all branches is a single point of failure.

prioritize ruthlessly

철저하게 우선순위를 정하다 · 자원이 부족할 때 꼭 필요한 일만 하자고 할 때

Until then, Sora, let's prioritize ruthlessly.

응용 연습
With two weeks left, we need to prioritize ruthlessly.

definition of done

완료 기준 · 마일스톤이나 작업이 끝났다고 판단하는 기준을 정할 때

Second, I want a written definition of done for each milestone.

응용 연습
Our definition of done includes passing the 72-hour stress test.

on the same page

같은 이해를 공유하는 · 결정 사항을 다시 확인해 모두의 이해를 맞출 때

Let me read back the decisions so we're all on the same page.

응용 연습
Before we escalate, let's make sure we're on the same page about the root cause.

Couldn't agree more

전적으로 동의합니다 · 상대 의견에 강하게 동의할 때

Couldn't agree more.

응용 연습
Couldn't agree more; we should add the test to the presubmit checks.

wrap up

마무리하다 · 회의나 논의를 끝낼 때

Then let's wrap up.

응용 연습
Let's wrap up and send the minutes within the hour.