SYSTEM SW / 2026-08-08 / Program kickoff
Orion·Orion Lite OS 업그레이드 프로그램 킥오프
출시된 Orion과 Orion Lite를 다음 안드로이드 버전으로 업그레이드하는 프로그램의 킥오프 회의입니다. 프로그램 관리, 플랫폼 프레임워크, 커널·BSP, SQE 팀이 개발 시작일, 베타와 정식 배포 일정, Atlas와의 인력 충돌, 커널 유지 여부를 논의합니다.
가상의 비즈니스 회의 · 중급~고급 · 2,220단어 · 약 18분
Good morning, everyone, and thank you for coming in on a Saturday. I know several of you were in the Atlas checkpoint at ten, so I'll try not to repeat things you've already heard today. I'm Joanne from Program Management, and I'll be running the OS upgrade program for Orion and Orion Lite. Let's go around the table.
Brian, Platform Framework. My team will do most of the heavy lifting on this one, since an OS upgrade is mostly a framework merge.
Elena, also Framework. I'll be the technical lead for the merge itself, and I'll coordinate with the app teams on compatibility.
Chris, Kernel and BSP. I'm here mainly to discuss whether we keep the current kernel or move to a newer one, and what that means for the vendor.
Minji, SQE lead for Orion. And Ryan is joining me because he'll own the carrier certification plan.
Hi, Ryan Cha, SQE. I coordinate with the carrier labs, so most of my questions today will be about dates.
Let me start with the background. Google's next Android release is planned for early December, according to the partner timeline Kevin shared last week. Our commitment to customers is that Orion gets the upgrade, and Orion Lite gets it as well, since both are within their support window. Last year, our competitors delivered their upgrades between four and ten weeks after Google's release. The business would like us to be at the front of that range this time.
So the headline target from the business is a stable rollout for Orion in mid-January, roughly six weeks after Google. Orion Lite would follow about a month later. I'll be honest: that target was set before anyone asked engineering, which is exactly why we're here today.
I appreciate you saying that up front. Mid-January would be ambitious even in a normal year, and this is not a normal year, because Atlas is pulling on the same framework engineers. I'd like to understand how much flexibility there is in that date before we commit to anything.
There's some. What the business really cares about is not being the last one. If we can give them a credible plan with a clear beta milestone, I think February is negotiable. What they won't accept is a vague answer.
Elena, let's start with the biggest piece of work. How big is the framework merge, and how long will it take?
Based on the developer preview we've already pulled, there are roughly fourteen hundred files where Google's changes overlap with our modifications. From experience, about seventy percent of those resolve mechanically. The remaining four hundred or so need someone who understands both sides. My estimate is six weeks for the merge to reach a booting, roughly functional build, and another four weeks to restore feature parity with our current Orion software.
So ten weeks of framework work before we have something we can seriously test. If we started on August 17th, that takes us to the end of October.
That's with a full team, though. Here's the problem. Atlas framework bring-up also starts in late August, and it needs about sixty percent of the same people. If I split the team, both programs slow down. Realistically, with the people I can spare, the upgrade merge takes closer to fourteen weeks.
Fourteen weeks puts us at the end of November, before Google's final release even ships. Is that actually a problem? We'd be merging against preview builds anyway.
It's not a problem by itself. But between the last preview and the final release, Google usually changes a few hundred files. We'd need a second, smaller merge in December. That typically takes two to three weeks, and it's the part that most often surprises people.
Chris, what about the kernel side? Do we need a new kernel for the upgrade?
Good news here, for once. Under Google's rules, devices that upgrade can keep their launch kernel branch, as long as it's still within its support period. Orion and Orion Lite are both on the 6.1 branch, which is supported well beyond next year. So we don't have to do a kernel uplift. That saves us easily two months of work and a lot of risk.
That's a relief. But the vendor side still changes, doesn't it? The new Android version comes with new vendor interface requirements.
Right. The kernel stays, but some hardware abstraction layers need updates to meet the new interface versions. For Orion, Qorvix has to deliver updated camera, audio, and graphics components. I asked them informally last week, and they said they could deliver a first drop by mid-October and a final one by mid-November. I'll get that in writing.
Mid-November for the final vendor drop is fine for us, as long as the first drop in October already has the new interfaces, even if the implementations are rough. We need the interfaces to compile the framework against.
I'll make that an explicit requirement when I talk to them. I'll also ask for their test results on the compatibility suites with each drop, because last year their first upgrade drop failed about three hundred vendor tests, and we only found out when we ran them ourselves two weeks later.
Let's talk about testing, because that's usually where upgrade schedules die. Minji, Ryan?
From SQE's side, an OS upgrade needs three things. First, our full regression suite, which takes about three weeks per round, and we always need at least two rounds. Second, an upgrade-specific test: we take devices with real user data on the old version, upgrade them, and make sure nothing is lost and every app still works. That's the one that catches the scariest bugs. Third, Google's compatibility test suites, which have to pass before we can ship at all.
And then there are the carriers. Orion is sold through forty-two carriers worldwide. The big ones in North America and Korea require their own certification of an OS upgrade, which takes between four and eight weeks after we submit. Some of them also have holiday freezes: two of the US carriers don't accept new submissions between December 15th and January 5th.
That holiday freeze is a big deal. If we can't submit before December 15th, those carriers effectively push us into February, no matter how fast we are.
Exactly. On the other hand, unlocked devices and markets without carrier certification, like most of Europe, could go earlier, as long as Google's compatibility tests pass. So we might want a split rollout: open markets first, then carrier markets as approvals come in.
Let me try to put this together into a draft plan, and you tell me where it breaks. Development starts on August 17th with a reduced framework team. Internal dogfood on preview-based software starts November 2nd. The final Google release lands in early December, and we finish the second merge by December 18th. A public beta for Orion opens on December 21st in Korea and the US. Stable rollout in open markets starts on February 1st, with carrier markets following through February.
November 2nd for dogfood is tight, given Brian's fourteen-week estimate. You'd be giving internal users a build that isn't feature complete. I'm okay with that for engineers, but not for the broader company dogfood population.
That's a good distinction. Let's say engineering dogfood on November 2nd, and company-wide dogfood on November 30th, once feature parity is restored.
That works for me. And for the public beta on December 21st, I'd want at least one week of company-wide dogfood on the final Google release first. December 18th to the 21st is only three days.
Then let's move the public beta to January 4th. That still gives us four weeks of beta before February 1st. Ryan, does that work with the carrier freeze?
Only if we submit to the US carriers before December 15th, which means submitting a build that isn't final yet. Some carriers accept a pre-final submission for early testing and then a quick delta review for the final build. I'd need to negotiate that with each of them, but it's been done before.
I want to flag something before we lock this. Everything we just said assumes the reduced framework team stays reduced, not that it shrinks further. If Atlas hits a crisis in October and pulls more people, this plan breaks. I'd like a rule that pulling people from the upgrade requires a conversation at the program director level, not just a hallway decision.
That's very reasonable, and I'll take it to the program directors on Monday. I'll present it as a dependency between the two programs, so it's visible to both sides.
Let's spend a few minutes on the public beta itself, since it's the first thing customers will see. How many participants are we aiming for, and what do we actually want to learn from it?
For a flagship upgrade, I'd aim for around twenty thousand participants across Korea and the US. That's enough to see crash patterns we'd never find in the lab, especially with third-party apps. What I want to learn most is the upgrade success rate and the top crashing apps after the upgrade, not opinions about new features.
I'd add one more goal: app compatibility. Every Android release changes some behaviors that apps depend on. In the beta, we should automatically report any app that crashes more than twice as often as it did on the old version, and share that list with our developer relations team every week.
One practical point. Beta users need a way back. If someone joins the beta and their banking app stops working, they need to be able to roll back to the stable version without losing data. Otherwise, we'll have angry customers and service center visits.
Rolling back without data loss is harder than it sounds, because the new version migrates databases to new formats. The safe approach is to back up the user data before the upgrade and restore it on rollback. It's doable, but it needs to be designed now, not in December.
Then let's make the rollback path a formal requirement for the beta. Elena, can you include it in the merge plan as its own work item, with an owner and a date?
Yes. I'll scope it this week and give you a realistic estimate by the fourteenth.
Now Orion Lite. The business wants it about a month after Orion. Is that realistic?
Most of the framework work is shared, so Orion Lite mainly needs its own device-specific integration and testing. Six weeks after Orion is realistic. Four weeks would mean overlapping testing with the Orion beta, and SQE would be stretched very thin.
I agree with Elena. Six weeks lets us reuse the same test devices and the same people. So Orion Lite stable around March 15th.
Let's list the top risks so I can put them in the plan. I have: Atlas pulling framework engineers, Qorvix vendor drops slipping, the carrier holiday freeze, and Google's final release moving. Anything else?
One more: data migration. Every OS upgrade changes some internal database formats. If the migration fails on even a small percentage of devices, users lose data, and that's the kind of thing that ends up in the news. I want the upgrade-specific test to start as early as engineering dogfood, not after the beta.
Agreed, and please include devices that are almost full. Storage-related migration failures almost always show up on devices with less than five percent free space.
Okay, let me summarize the plan. Development starts August 17th with a reduced framework team. Engineering dogfood November 2nd. Company dogfood November 30th. Second merge complete December 18th. Pre-final carrier submissions before December 15th. Public beta January 4th. Orion stable in open markets February 1st, carrier markets through February. Orion Lite stable around March 15th. Kernel stays on 6.1. Does anyone object?
No objection, with the staffing rule we discussed.
Noted. Action items: Elena, share the detailed merge plan and the list of risky areas by August 14th. Chris, get written confirmation of the Qorvix vendor drop dates and the interface requirement by August 12th. Minji, design the upgrade-specific test, including near-full devices, by the end of August. Ryan, start negotiating pre-final submissions with the US and Korean carriers. Brian, confirm the names of the engineers assigned to the upgrade. And I'll take the staffing rule and the February date to the program directors on Monday.
I'll start with the two US carriers that have the holiday freeze, since they're the biggest risk to the date. If either of them refuses a pre-final submission, I'll let you know immediately, so we can decide whether to move the beta or accept a later date for those markets.
Thank you, everyone. I think this is a plan I can defend, and that's what I needed. We'll meet every other Saturday at 2 p.m. Korea time while the program is ramping up. The next meeting is August 22nd, same room. By then, I'd like the merge plan, the vendor dates, and a first read from the carriers.
Sounds good. I'll start pulling the latest preview into a branch on Monday, so we're ready to go on the seventeenth.
Thanks, Joanne. It's a relief to start an upgrade program with realistic dates for once.
좋은 아침입니다, 여러분. 토요일에 나와 주셔서 감사합니다. 몇 분은 10시 Atlas 점검 회의에 계셨던 걸로 알고 있으니, 오늘 이미 들으신 내용은 반복하지 않도록 하겠습니다. 저는 프로그램 관리팀의 Joanne이고, Orion과 Orion Lite의 OS 업그레이드 프로그램을 운영하게 됩니다. 돌아가며 소개하죠.
플랫폼 프레임워크팀 Brian입니다. OS 업그레이드는 대부분 프레임워크 머지라서, 이번 건은 저희 팀이 대부분의 힘든 일을 맡게 될 겁니다.
같은 프레임워크팀 Elena입니다. 머지 자체의 기술 리드를 맡고, 호환성 문제로 앱 팀들과 조율하겠습니다.
커널·BSP 팀 Chris입니다. 주로 현재 커널을 유지할지 새 커널로 옮길지, 그리고 그게 벤더에게 어떤 의미인지 논의하려고 왔습니다.
Orion SQE 리드 민지입니다. 그리고 Ryan은 통신사 인증 계획을 맡을 거라 같이 왔습니다.
안녕하세요, SQE 차라이언입니다. 통신사 랩들과 조율하는 일을 해서, 오늘 제 질문은 대부분 날짜에 관한 거예요.
배경부터 말씀드리겠습니다. 지난주 Kevin이 공유한 파트너 일정에 따르면 Google의 다음 안드로이드 릴리스는 12월 초로 계획돼 있습니다. 고객에 대한 저희 약속은 Orion과 Orion Lite 모두 지원 기간 안에 있으니 둘 다 업그레이드를 받는다는 겁니다. 작년에 경쟁사들은 Google 릴리스 후 4주에서 10주 사이에 업그레이드를 내놓았습니다. 사업부는 이번에 저희가 그 범위의 앞쪽에 있기를 원합니다.
그래서 사업부의 핵심 목표는 Orion 정식 배포를 1월 중순, 즉 Google 이후 약 6주에 하는 겁니다. Orion Lite는 그로부터 한 달 정도 뒤에 따라가고요. 솔직히 말씀드리면, 이 목표는 엔지니어링에 묻기 전에 정해졌고, 그래서 오늘 이 자리가 필요한 겁니다.
그걸 처음부터 말씀해 주셔서 감사합니다. 1월 중순은 평범한 해에도 야심 찬 목표인데, 올해는 Atlas가 같은 프레임워크 엔지니어들을 끌어가고 있어서 평범한 해가 아닙니다. 뭔가를 약속하기 전에 그 날짜에 얼마나 유연성이 있는지 이해하고 싶습니다.
어느 정도는 있습니다. 사업부가 진짜 신경 쓰는 건 꼴찌가 되지 않는 겁니다. 명확한 베타 마일스톤이 있는 신뢰할 만한 계획을 주면, 2월은 협상 가능하다고 봅니다. 사업부가 받아들이지 않는 건 모호한 답변입니다.
Elena, 가장 큰 작업부터 시작하죠. 프레임워크 머지 규모가 얼마나 되고, 얼마나 걸릴까요?
이미 받아 둔 개발자 프리뷰 기준으로, Google의 변경과 저희 수정이 겹치는 파일이 약 1,400개입니다. 경험상 그중 70% 정도는 기계적으로 해결됩니다. 나머지 400개 정도는 양쪽을 다 이해하는 사람이 필요합니다. 제 추정으로는 머지가 부팅되고 대략 동작하는 빌드에 도달하는 데 6주, 현재 Orion 소프트웨어와 기능 동등성을 회복하는 데 4주가 더 걸립니다.
그러니까 제대로 테스트할 수 있는 결과물이 나오기까지 프레임워크 작업만 10주군요. 8월 17일에 시작하면 10월 말이 되네요.
그런데 그건 팀 전원이 붙었을 때 얘기입니다. 문제는 이겁니다. Atlas 프레임워크 브링업도 8월 말에 시작하는데, 같은 사람들 중 약 60%가 필요합니다. 팀을 나누면 두 프로그램 모두 느려집니다. 현실적으로 제가 내줄 수 있는 인원으로는 업그레이드 머지가 14주 가까이 걸립니다.
14주면 11월 말인데, Google 최종 릴리스가 나오기도 전이네요. 그게 실제로 문제가 되나요? 어차피 프리뷰 빌드 기준으로 머지하게 될 텐데요.
그 자체로는 문제가 아닙니다. 하지만 마지막 프리뷰와 최종 릴리스 사이에 Google은 보통 수백 개 파일을 바꿉니다. 12월에 두 번째, 더 작은 머지가 필요합니다. 보통 2~3주 걸리는데, 사람들이 가장 자주 놀라는 부분이 바로 그겁니다.
Chris, 커널 쪽은요? 업그레이드에 새 커널이 필요한가요?
이번엔 좋은 소식입니다. Google 규정상 업그레이드하는 단말은 출시 커널 브랜치가 아직 지원 기간 안에 있으면 그대로 유지할 수 있습니다. Orion과 Orion Lite 모두 6.1 브랜치인데, 내년 이후까지 충분히 지원됩니다. 그래서 커널 업리프트를 할 필요가 없습니다. 그것만으로 두 달 치 작업과 많은 위험을 덜 수 있습니다.
다행이네요. 그런데 벤더 쪽은 여전히 바뀌죠? 새 안드로이드 버전에는 새로운 벤더 인터페이스 요구사항이 따라오잖아요.
맞습니다. 커널은 유지되지만, 일부 HAL은 새 인터페이스 버전을 맞추기 위해 업데이트가 필요합니다. Orion의 경우 Qorvix가 카메라, 오디오, 그래픽 구성 요소를 업데이트해서 전달해야 합니다. 지난주에 비공식적으로 물어봤는데, 10월 중순까지 첫 드롭, 11월 중순까지 최종 드롭을 줄 수 있다고 했습니다. 서면으로 받아 두겠습니다.
최종 벤더 드롭이 11월 중순이면 저희는 괜찮습니다. 단, 10월 첫 드롭에 구현이 엉성하더라도 새 인터페이스는 이미 들어가 있어야 합니다. 프레임워크를 그 인터페이스에 맞춰 컴파일해야 하거든요.
그들과 이야기할 때 그걸 명시적인 요구사항으로 넣겠습니다. 그리고 드롭마다 호환성 스위트 테스트 결과도 요청하겠습니다. 작년에 그쪽 첫 업그레이드 드롭이 벤더 테스트 약 300개에서 실패했는데, 2주 뒤에 저희가 직접 돌려 보고서야 알았거든요.
테스트 이야기를 하죠. 보통 업그레이드 일정이 무너지는 곳이 거기니까요. 민지 님, Ryan?
SQE 입장에서 OS 업그레이드에는 세 가지가 필요합니다. 첫째, 전체 회귀 스위트인데, 한 라운드에 약 3주 걸리고 항상 최소 두 라운드는 필요합니다. 둘째, 업그레이드 전용 테스트입니다. 이전 버전에서 실제 사용자 데이터가 있는 단말을 업그레이드해서, 아무것도 손실되지 않고 모든 앱이 여전히 동작하는지 확인합니다. 가장 무서운 버그를 잡아내는 테스트가 바로 이겁니다. 셋째, Google의 호환성 테스트 스위트인데, 이걸 통과해야 출시 자체가 가능합니다.
그리고 통신사가 있습니다. Orion은 전 세계 42개 통신사를 통해 판매됩니다. 북미와 한국의 대형 통신사들은 OS 업그레이드에 대해 자체 인증을 요구하는데, 제출 후 4주에서 8주가 걸립니다. 일부는 연말 동결 기간도 있습니다. 미국 통신사 두 곳은 12월 15일부터 1월 5일까지 새 제출을 받지 않습니다.
그 연말 동결은 큰 문제네요. 12월 15일 전에 제출하지 못하면, 우리가 아무리 빨라도 그 통신사들 때문에 사실상 2월로 밀리겠네요.
정확합니다. 반면 자급제 단말이나 대부분의 유럽처럼 통신사 인증이 없는 시장은, Google 호환성 테스트만 통과하면 더 일찍 나갈 수 있습니다. 그래서 단계적 배포를 원할 수도 있습니다. 개방 시장 먼저, 그다음 승인이 나는 대로 통신사 시장으로요.
이걸 종합해서 계획 초안을 만들어 볼 테니, 어디서 깨지는지 말씀해 주세요. 개발은 8월 17일 축소된 프레임워크 팀으로 시작합니다. 프리뷰 기반 소프트웨어로 내부 도그푸드를 11월 2일 시작합니다. Google 최종 릴리스가 12월 초에 나오고, 12월 18일까지 두 번째 머지를 마칩니다. Orion 공개 베타는 12월 21일 한국과 미국에서 시작합니다. 개방 시장 정식 배포는 2월 1일 시작하고, 통신사 시장은 2월 내내 순차적으로 따라갑니다.
Brian의 14주 추정을 고려하면 11월 2일 도그푸드는 빠듯합니다. 기능이 완성되지 않은 빌드를 내부 사용자에게 주게 되는 거죠. 엔지니어 대상이라면 괜찮지만, 회사 전체 도그푸드 대상으로는 안 됩니다.
좋은 구분이네요. 엔지니어링 도그푸드는 11월 2일, 기능 동등성이 회복된 후 회사 전체 도그푸드는 11월 30일로 하죠.
저는 그거면 됩니다. 그리고 12월 21일 공개 베타의 경우, 그 전에 Google 최종 릴리스 기준으로 회사 전체 도그푸드를 최소 일주일은 하고 싶습니다. 12월 18일부터 21일까지는 3일뿐이에요.
그럼 공개 베타를 1월 4일로 옮기죠. 그래도 2월 1일 전까지 4주의 베타 기간이 있습니다. Ryan, 통신사 동결 기간과 맞나요?
12월 15일 전에 미국 통신사에 제출해야만 가능한데, 그러면 아직 최종이 아닌 빌드를 제출해야 합니다. 일부 통신사는 조기 테스트용으로 최종 전 빌드를 받고, 최종 빌드에 대해서는 빠른 변경분 검토를 해 줍니다. 각 통신사와 협상해야 하지만, 전에도 해 본 적이 있습니다.
확정하기 전에 짚고 싶은 게 있습니다. 방금 말한 모든 건 축소된 프레임워크 팀이 그 규모를 유지한다는 전제입니다. 더 줄어들지 않는다는 거죠. 10월에 Atlas가 위기를 맞아 사람을 더 데려가면 이 계획은 깨집니다. 업그레이드에서 인원을 빼려면 복도에서 정하는 게 아니라 프로그램 디렉터 수준의 논의를 거치도록 하는 규칙이 있었으면 합니다.
아주 합리적이네요. 월요일에 프로그램 디렉터들에게 가져가겠습니다. 두 프로그램 간의 의존성으로 제시해서 양쪽 모두에게 보이게 하겠습니다.
고객이 가장 먼저 보게 될 공개 베타 자체에 대해 몇 분 이야기하죠. 참가자를 몇 명 정도 목표로 하고, 거기서 실제로 무엇을 알고 싶은 건가요?
플래그십 업그레이드라면 한국과 미국에 걸쳐 약 2만 명 정도를 목표로 하겠습니다. 랩에서는 절대 찾지 못할 크래시 패턴, 특히 서드파티 앱 관련 패턴을 보기에 충분한 수입니다. 가장 알고 싶은 건 새 기능에 대한 의견이 아니라 업그레이드 성공률과 업그레이드 후 가장 많이 크래시 나는 앱들입니다.
목표를 하나 더 추가하고 싶어요. 앱 호환성입니다. 안드로이드 릴리스마다 앱이 의존하는 일부 동작이 바뀝니다. 베타에서 이전 버전보다 두 배 이상 자주 크래시 나는 앱을 자동으로 보고하고, 그 목록을 매주 개발자 관계팀과 공유해야 합니다.
실무적인 포인트 하나요. 베타 사용자에게는 되돌아갈 방법이 필요합니다. 누군가 베타에 참여했는데 은행 앱이 안 되면, 데이터를 잃지 않고 정식 버전으로 롤백할 수 있어야 합니다. 그렇지 않으면 화난 고객과 서비스 센터 방문이 생길 겁니다.
데이터 손실 없이 롤백하는 건 생각보다 어렵습니다. 새 버전이 데이터베이스를 새 형식으로 마이그레이션하거든요. 안전한 방법은 업그레이드 전에 사용자 데이터를 백업하고 롤백할 때 복원하는 겁니다. 가능하지만, 12월이 아니라 지금 설계해야 합니다.
그럼 롤백 경로를 베타의 공식 요구사항으로 하죠. Elena, 머지 계획에 담당자와 날짜가 있는 별도 작업 항목으로 넣어 줄 수 있나요?
네. 이번 주에 범위를 잡고 14일까지 현실적인 추정치를 드리겠습니다.
이제 Orion Lite입니다. 사업부는 Orion보다 한 달 정도 뒤를 원합니다. 현실적인가요?
프레임워크 작업 대부분이 공유되니까, Orion Lite는 주로 자체 단말 특화 통합과 테스트만 필요합니다. Orion 이후 6주는 현실적입니다. 4주면 Orion 베타 테스트와 겹쳐서 SQE가 매우 빠듯해집니다.
Elena 말에 동의합니다. 6주면 같은 테스트 단말과 같은 인력을 재사용할 수 있습니다. 그러면 Orion Lite 정식은 3월 15일경이네요.
주요 위험을 나열해서 계획에 넣겠습니다. 제가 정리한 건 Atlas가 프레임워크 엔지니어를 데려가는 것, Qorvix 벤더 드롭 지연, 통신사 연말 동결, Google 최종 릴리스 일정 변경입니다. 다른 게 있나요?
하나 더 있습니다. 데이터 마이그레이션이요. 모든 OS 업그레이드는 일부 내부 데이터베이스 형식을 바꿉니다. 아주 작은 비율의 단말에서라도 마이그레이션이 실패하면 사용자가 데이터를 잃고, 그런 건 뉴스에 나는 종류의 일입니다. 업그레이드 전용 테스트를 베타 이후가 아니라 엔지니어링 도그푸드 때부터 시작하고 싶습니다.
동의합니다. 그리고 저장 공간이 거의 찬 단말도 포함해 주세요. 스토리지 관련 마이그레이션 실패는 거의 항상 여유 공간이 5% 미만인 단말에서 나타납니다.
좋습니다. 계획을 요약하겠습니다. 개발은 8월 17일 축소된 프레임워크 팀으로 시작합니다. 엔지니어링 도그푸드 11월 2일, 회사 도그푸드 11월 30일, 두 번째 머지 완료 12월 18일, 최종 전 통신사 제출은 12월 15일 이전입니다. 공개 베타 1월 4일, Orion 개방 시장 정식 배포 2월 1일, 통신사 시장은 2월 내내 진행합니다. Orion Lite 정식은 3월 15일경입니다. 커널은 6.1을 유지합니다. 반대하시는 분 있나요?
논의한 인력 규칙이 있다면 반대하지 않습니다.
알겠습니다. 실행 항목입니다. Elena는 8월 14일까지 상세 머지 계획과 위험 영역 목록을 공유해 주세요. Chris는 8월 12일까지 Qorvix 벤더 드롭 날짜와 인터페이스 요구사항을 서면으로 확인받아 주세요. 민지 님은 8월 말까지 거의 꽉 찬 단말을 포함한 업그레이드 전용 테스트를 설계해 주세요. Ryan은 미국과 한국 통신사와 최종 전 제출 협상을 시작해 주세요. Brian은 업그레이드에 배정된 엔지니어 명단을 확정해 주세요. 그리고 저는 월요일에 인력 규칙과 2월 날짜를 프로그램 디렉터들에게 가져가겠습니다.
날짜에 가장 큰 위험이 되는 연말 동결이 있는 미국 통신사 두 곳부터 시작하겠습니다. 둘 중 하나라도 최종 전 제출을 거부하면 바로 알려 드려서, 베타를 옮길지 아니면 그 시장들은 더 늦은 날짜를 받아들일지 결정할 수 있게 하겠습니다.
모두 감사합니다. 제가 설득할 수 있는 계획이 된 것 같고, 그게 제게 필요했던 겁니다. 프로그램이 본격화되는 동안 격주 토요일 한국 시간 오후 2시에 모이겠습니다. 다음 회의는 8월 22일, 같은 회의실입니다. 그때까지 머지 계획, 벤더 날짜, 그리고 통신사들의 첫 반응을 받아 보고 싶습니다.
좋습니다. 17일에 바로 시작할 수 있도록 월요일부터 최신 프리뷰를 브랜치로 가져오기 시작하겠습니다.
고마워요, Joanne. 이번만큼은 현실적인 날짜로 업그레이드 프로그램을 시작하게 돼서 마음이 놓이네요.
토요일에 출근해 준 것 · 주말에 회의에 참석한 사람들에게 감사할 때
Good morning, everyone, and thank you for coming in on a Saturday.
응용 연습
Thanks for coming in on a Saturday to help with the release.
가장 힘든 일을 대부분 맡다 · 작업의 핵심 부담을 어느 팀이 지는지 말할 때
My team will do most of the heavy lifting on this one, since an OS upgrade is mostly a framework merge.
응용 연습
The vendor will do most of the heavy lifting on the modem fix.
그 범위의 앞쪽에 · 경쟁사 대비 빠른 위치에 서고 싶다고 말할 때
The business would like us to be at the front of that range this time.
응용 연습
We want our security patch delivery to be at the front of that range.
처음부터, 미리 솔직하게 · 중요한 사실을 처음부터 밝힌 데 대해 말할 때
I appreciate you saying that up front.
응용 연습
Let's be clear up front about what's out of scope.
같은 (자원을) 끌어가는 · 여러 프로젝트가 같은 인력이나 자원을 두고 경쟁할 때
Mid-January would be ambitious even in a normal year, and this is not a normal year, because Atlas is pulling on the same framework engineers.
응용 연습
Three programs are pulling on the same test devices this month.
협상 가능하다 · 조건이나 일정에 유연성이 있음을 말할 때
If we can give them a credible plan with a clear beta milestone, I think February is negotiable.
응용 연습
The feature list is negotiable, but the security deadline isn't.
기계적으로 해결되다 · 머지 충돌 등이 단순 작업으로 처리될 때
From experience, about seventy percent of those resolve mechanically.
응용 연습
Most of the conflicts resolve mechanically with the merge script.
이번만큼은 · 평소와 달리 좋은 일이 있을 때
Good news here, for once.
응용 연습
For once, the vendor delivered a day early.
업그레이드 일정이 무너지는 곳 · 일정의 가장 취약한 단계를 강조할 때
Let's talk about testing, because that's usually where upgrade schedules die.
응용 연습
Carrier certification is where launch schedules die.
큰 문제, 중요한 일 · 사안의 중대성을 강조할 때
That holiday freeze is a big deal.
응용 연습
Losing two weeks of testing is a big deal at this stage.
어디서 깨지는지, 어디가 문제인지 · 제안을 하며 약점을 지적해 달라고 할 때
Let me try to put this together into a draft plan, and you tell me where it breaks.
응용 연습
Here's the rollout plan; tell me where it breaks.
짚고 넘어가고 싶은 게 있다 · 결정 전에 위험이나 전제 조건을 강조할 때
I want to flag something before we lock this.
응용 연습
I want to flag something about the test device budget.
복도에서 즉흥적으로 내리는 결정 · 공식 절차 없이 비공식적으로 내려지는 결정을 경계할 때
I'd like a rule that pulling people from the upgrade requires a conversation at the program director level, not just a hallway decision.
응용 연습
Changing the freeze date shouldn't be a hallway decision.
매우 빠듯하게 분산된 · 인력이나 자원이 부족한 상태를 표현할 때
Four weeks would mean overlapping testing with the Orion beta, and SQE would be stretched very thin.
응용 연습
With three launches in one month, the kernel team is stretched very thin.
설득력 있게 방어할 수 있는 계획 · 윗선에 보고할 때 근거가 탄탄한 계획을 말할 때
I think this is a plan I can defend, and that's what I needed.
응용 연습
Give me numbers so I have a plan I can defend to the director.